Electricity announces the date of starting the Gulf interconnection project … and important details

Electricity announces the date of starting the Gulf interconnection project … and important details

05/11/2021 03:46:57

Electricity announces the date of starting the Gulf interconnection project ... and important detailsThe Ministry of Electricity will soon start the Gulf interconnection project, after it was agreed to be financed by Gulf trust funds.

The ministry’s spokesperson, Ahmad al-Abadi, said in a press statement, “The ministry is keen and serious about the issue of diversifying energy sources and approving electrical interconnection projects with neighboring countries, as it signed framework agreements with the Jordan Gulf Link Authority.”
He added, “Iraq has accomplished 81 percent of its Gulf Ministry’s commitments to the project with the Gulf Linkage Commission, which has resumed conducting coordination meetings to resume work, where the agreement has been completed to cover the value of the credit and cover the project. In the form of installments, as they will be fixed assets for the Iraqi state. ”
Al-Abadi stated, “The two sides agreed to establish a line to connect the Al-Zour station inside Kuwaiti territory and the Faw inside Iraqi lands, and this does not mean the link with the State of Kuwait because the connection with the Iraqi Gulf Linkage Authority, but the line is 300 km long, of which 220 km is inside Kuwaiti territory and 80 km is inside the land. it is expected to be launched work on the project within a month from now and the side of the Gulf in the process of scanning paths lines and study the appropriate anchor points of the project to complete. ”
and that” the first with the Gulf Interconnection Authority agreement undergone some innovations have been modified contract formula again in terms of tariffs, obligations and financing And now things are clearer for the Gulf side, and understanding the great desire of Iraq to complete the project.
Al-Abadi expected that “the summer of 2022 will witness the completion of the first phase of the project, which provides for the supply of energy estimated at 500 megawatts to Basra Governorate.”
He clarified that “the electrical interconnection project with Jordan witnessed the signing of a framework agreement requiring the connection of power lines through the construction of an existing wind line and the establishment of the Al-Qaim transforming station of 400 kV, as the implementation of which was referred to the General Electric Company.”
And he indicated that “the initiation and completion of this work depends on finding loans or providing the funds necessary for implementation,” stressing that “the company has proceeded to study the examination of soil and its absence of military remnants, given that the area was occupied by ISIS terrorist gangs, in addition to coordination with the departments and the overlapping parties. And examine the points of connection and determine the paths of the lines.
And he indicated that “the time limit for the completion of the first phase of the project is 26 months, and it is required to pay an energy amounting to 150 megawatts to the western governorates and the Iraqi regime, which will reach 900 megawatts.”
Al-Abbadi added that “all the electrical interconnection projects and the future of Iraq could not be conceived on the basis of importing electricity only, but also on the mutual benefit of energy and the creation, reliability and great stability of the electrical network. “Through the conveying lines, and thus it will benefit from the technical aspects, and may return economic rent and tariffs as a result of passing on energy.”